ADDONS.MOZILLA.ORG (AMO)

AMO 4.0.4 – Status: Released December 11th
AMO 4.0.5 – Status: In Process

FIREFOX

Fx 2.0.0.19 -> 3.0.5 Major Update – Status: Pending

  • Currently scheduled for early January after Thunderbird 2.0.0.19
  • Will be dependent on localization of the new major update text
Fx 2.0.0.19 & Fx 3.0.5 -Status: Released

  • Shipped Firefox 2.0.0.19 and 3.0.5 on Tuesday
  • Noticed that the 2.0.0.19 release was incomplete
Fx 2.0.0.20 -Status: Released

  • Shipped 2.0.0.20 release on Thursday

Fx 3.0.6 – Status: Tree Opening Pending

  • Proposed schedule now on wiki
  • QA: Started triage for 3.0.6 [ss]
  • Targeted release is early February
  • Schedule (Estimated)
    • Tree opens: December 5
    • Code freeze: January 6 11:59pm
    • QA (Part 1) starts: January 7, 2009
    • Builds start: January 19, 2009
    • QA (Part 2) starts: January 20, 2009
    • Release to beta channel: January 27, 2009
    • Final Release: February 3, 2009

Fx 3.1b3 (Shiretoko) – Status: In Development

  • No Report
  • proposed schedule as follows:

    • Dec 31 – string freeze
    • Jan 13 – code freeze
    • Jan 19 – QA start
    • Jan 26 – ship to users
    • if you have counter proposals or problems, please come to tomorrow’s development meeting.

GECKO

Gecko 1.9.1

THUNDERBIRD

TBird 2.0.0.19 -Status: Released to Beta

  • Schedule now available on the wiki.
  • Going forward, plan to release Thunderbird 2 updates once every eight weeks
  • Currently planning release for early January
  • Beta release later this week
  • QA: Moved Thunderbird 2 to a 2 month release cycle [ss]
  • Schedule (Estimated)

    • Code freeze:  November 17, 11:59pm PDT
    • Builds start: December 9 or 10 (depending on Firefox 2.0.0.19 beta period)
    • QA starts: December 10 or 11
    • Release to beta channel: December 17 or 18
    • Final Release: As late as January 6 (pending QA and build resources in December)

TBird 3.0b2 (Shredder) – Status: In Process

  • Beta 2 work and planning is underway
  • Schedule (will re-evaluate in early January, hope to be able to accelerate:)

    • String Freeze: December 31st
    • Code freeze: January 13th
    • Builds start: TBD
    • QA starts: January 19th
    • Release to beta channel: TBD
    • Final Release: January 26th

Complete Meeting Notes